Profitability index and internal rate of return

Edexcel IAL Accounting · WAC12 Corporate and Management Accounting

Two more discounted methods support NPV. The profitability index compares the present value of the returns with the investment; the internal rate of return finds the discount rate at which NPV is zero.

Practise this in the app: instant marking and a fix for every mistake. Free, no email needed to start.

Practise this lesson

Profitability index (PI)

PI = present value of future net cash inflows / initial investment

Some texts use NPV / initial investment instead (above 0 is acceptable); the June 2025 examiners accepted both methods, so state the formula you use.

Internal rate of return (IRR)

The IRR is the discount rate that makes NPV = 0: the project's own rate of return.

1. Calculate NPV at a lower rate (giving a positive NPV) and at a higher rate (giving a negative NPV).

2. Interpolate:

IRR = L + [NPV at L / (NPV at L - NPV at H)] x (H - L)

where L and H are the lower and higher rates. (This is the formula in the WAC12 mark schemes.)

Decision: accept if IRR is above the cost of capital (WACC).

Worked IRR

Cost £120,000; net inflows £40,000 a year for 4 years.

YearCash flow £Factor 10%PV 10% £Factor 14%PV 14% £
0(120,000)1.000(120,000)1.000(120,000)
140,0000.90936,3600.87735,080
240,0000.82633,0400.76930,760
340,0000.75130,0400.67527,000
440,0000.68327,3200.59223,680
NPV6,760(3,480)

Comparing the methods

Worked example

Using the table, calculate the IRR and the profitability index at 10%.

  1. IRR = 10 + [6,760 / (6,760 - (-3,480))] x 4
  2. = 10 + 0.6602 x 4 = 12.64%
  3. PI = 126,760 / 120,000 = 1.06

Answer: IRR = 12.64%; PI = 1.06

Key idea: PI = PV of inflows / initial investment (accept above 1, rank under capital rationing); IRR = L + NPV_L / (NPV_L - NPV_H) x (H - L) (accept if above the cost of capital).

Check yourself

  1. The present value of a project's future net cash inflows is £345,000 and its initial cost is £300,000. Calculate the profitability index.
    Show answer

    1.15. 345,000 / 300,000 = 1.15.

  2. A project has an NPV of £18,000 at 8% and -£6,000 at 14%. Estimate the IRR to 1 decimal place.
    Show answer

    12.5 %. 8 + 18,000 / 24,000 x 6 = 12.5%.

  3. NPV at 10% is £4,250 and NPV at 15% is -£2,750. Estimate the IRR to 2 decimal places.
    Show answer

    13.04 %. 10 + 4,250 / 7,000 x 5 = 13.04%.

  4. A project costs £500,000 and has an NPV of £60,000. Calculate the PI using PV of inflows / initial cost.
    Show answer

    1.12. PV of inflows = 560,000; PI = 560,000 / 500,000 = 1.12.

  5. A company has £1,000,000 to invest and several projects with positive NPVs costing more than that in total. Which measure helps rank them?
    • Payback period alone
    • Gross profit margin
    • Dividend cover
    • Profitability index
    Show answer

    Profitability index. PI shows the NPV generated per £1 invested.

  6. A project's IRR is 13.5% and the company's WACC is 11%. What does this suggest?
    • Reject: IRR should be below WACC
    • Accept: the project's return exceeds the cost of capital
    • The NPV at 11% is negative
    • The payback period is 13.5 years
    Show answer

    Accept: the project's return exceeds the cost of capital. IRR above the cost of capital means NPV at that cost is positive.

  7. Project A has the higher NPV but project B has the higher IRR. They are mutually exclusive. Which should usually be chosen?
    • B, because a percentage is always better
    • Neither
    • Whichever has the shorter life
    • A, because NPV measures the increase in shareholders' wealth
    Show answer

    A, because NPV measures the increase in shareholders' wealth. NPV is the preferred method when rankings conflict.

Practise with instant feedback