All subjects · Information Technology · WIT11 2 hour written exam on IT systems, networks and data
Flowcharts
Edexcel IAL Information Technology · WIT11 2 hour written exam on IT systems, networks and data
Spec points 4.3.1 and 4.3.2: why flowcharts are needed, and how to interpret and create them for a scenario. The June 2024 paper had a 6-mark flowchart for a website registration process; each mark was a correct step, and checking for an already registered email was the step most often missed.
Why flowcharts
A flowchart shows the sequence of steps in a process or algorithm, including decisions and loops. Benefits: easy to follow for non-specialists; shows logic clearly so errors and missing steps can be found before building (in June 2025 most candidates earned the first mark for a benefit such as 'easily understood' or 'finding errors', but the linked expansion was the mark most often missed); helps communicate a design between users and developers; can be used to plan code and tests.
Symbols
| Symbol | Shape | Use |
|---|---|---|
| Terminator | Rounded rectangle (oval) | Start and End |
| Process | Rectangle | An action, for example 'Generate registration number' |
| Subprocess (predefined process) | Rectangle with double vertical sides | A process defined elsewhere, for example 'Validate form' |
| Decision | Diamond | A question with two exits labelled Yes and No |
| Input/Output | Parallelogram | Data in or out, for example 'Display error message', 'Enter email' |
| Flow line | Arrow | Shows the direction of the sequence |
Symbol names from Appendix 7 of the specification
Creating a flowchart: the registration example
Scenario: a user fills in first name, last name and email, then clicks Submit or Cancel.
1. Start. 2. Input: user completes the form. 3. Decision: Cancel clicked? Yes: End. 4. Decision: all fields valid? No: output error message, loop back to the form. 5. Decision: email already registered (search the database)? Yes: output 'already registered', loop back. 6. Process: store details in the database. 7. Process: generate a unique registration number. 8. Output: display the number. 9. End.
Tips: every decision has exactly two labelled exits; every path reaches End; loops go back with an arrow; use the correct shape for each step; connect every element.
Worked example
A flowchart sets total to 0, then for each number in the list [12, 7, 15, 3, 9] asks 'Is number > 8?'; if Yes it adds the number to total. After the last number it outputs total. What is output?
- Numbers greater than 8: [12, 15, 9].
- Total = 12 + 15 + 9 = 36.
Answer: 36
Check yourself
- Which flowchart symbol is used for a decision?
- Parallelogram
- Diamond
- Rounded rectangle
- Rectangle
Show answer
Diamond. Decisions have Yes and No exits.
- Which symbol should 'Display error message' use?
- Diamond (decision)
- Terminator
- Data store
- Parallelogram (input/output)
Show answer
Parallelogram (input/output). Displaying is output.
- Which symbol marks the start and end of a flowchart?
- Process
- Terminator
- Decision
- Subprocess
Show answer
Terminator. Rounded terminators begin and end.
- A flowchart sets count to 0 and total to 0. It repeats: add 4 to total, add 1 to count, until total > 15. Then it outputs count. What is output?
Show answer
4. Totals 4, 8, 12, 16: the loop stops after the 4th time, so count = 4.
- Using the flowchart in the worked example, what is output for the list [9, 2, 20, 8, 11]?
Show answer
40. 9 + 20 + 11 = 40 (8 is not greater than 8).
- A registration flowchart must stop a person registering twice with the same email. Describe the step needed.
Show answer
After validation, search the database for the email; a decision asks whether it is already registered, and if Yes an error message is shown and the user returns to the form.. Search, decision, error path.
- Which symbol represents a subprocess such as 'Validate form' defined elsewhere?
- Rectangle with double vertical sides
- Plain rectangle
- Diamond
- Parallelogram
Show answer
Rectangle with double vertical sides. Predefined processes have double sides.
Sources
- Pearson Edexcel International Advanced Level in Information Technology specification (2018), Unit 1
- Pearson Edexcel IAL Information Technology WIT11/01 question paper, June 2024
- Pearson Edexcel IAL Information Technology WIT11/01 examiner report, June 2024
- Pearson Edexcel IAL Information Technology WIT11/01 examiner report, June 2025
Last updated 8 November 2026. Spotted a mistake? Tell us.