Total float and Gantt charts
Float tells you how much an activity can be delayed without delaying the whole project. A Gantt (cascade) chart shows this at a glance.
Total float
Total float = latest finish time - duration - earliest start time. Earliest start = early time of the start event; latest finish = late time of the end event. Critical activities have zero float. Show all three numbers in your working.
Gantt (cascade) chart
Draw a time axis. Put critical activities in a row along the top. Below, draw each non-critical activity as a bar starting at its earliest start time, with its float shown as a dotted or shaded extension. The bar can slide right within the float.
Reading the chart
At a given time, an activity must be happening if it cannot avoid that time: latest start ≤ t and earliest finish ≥ t + 1 for the interval from t to t + 1. It may be happening if it could be scheduled across that time. Read the scale carefully: activities run from the start of one time unit to the start of another.
Limits
A Gantt chart shows timing and flexibility but not dependence: delaying one activity within its float can reduce the float of activities after it.
Worked example
Find the total float of activity D in project J.
- Earliest start of D = 4
- Latest finish of D = 14
- Float = 14 - 5 - 4 = 5
Answer: Total float of D = 5 days
Check yourself
- Find the total float of activity E in project J.
Show answer
3 days. 14 - 4 - 7 = 3.
- Find the total float of activity B in project J.
Show answer
1 days. 7 - 6 - 0 = 1.
- Find the total float of activity I in project J.
Show answer
3 days. 19 - 3 - 13 = 3.
- Which activities of project J must be happening during the interval from time 7 to time 8?
- F, D, E
- E
- B, F
- F
Show answer
F. Must happen: latest start ≤ 7 and earliest finish ≥ 8. Only F qualifies; D and E could also be scheduled then, but have enough float to avoid it.
- On a cascade chart, where are the critical activities drawn?
- At the bottom with their floats
- In a single row along the top
- In a column on the left
- Anywhere, with no float shown
Show answer
In a single row along the top. Critical activities fill the whole project time end to end, so they form one row along the top.
- Activities D and G in project J are in sequence and each shows float on the Gantt chart. If D is delayed by 3 days, what happens to G?
- Nothing happens to G
- The project is delayed
- G becomes a dummy
- G's available float is reduced
Show answer
G's available float is reduced. D has float 5 and G has float 3; some of D's float is shared with G, so delaying D uses up float that G could have used. The project is not delayed while the delay stays within D's float.
- What does a total float of zero tell you?
- The activity can start at any time
- The activity is critical: any delay delays the project
- The activity takes no time
- The activity is a dummy
Show answer
The activity is critical: any delay delays the project. Zero float means no slack at all.
Sources
- Pearson Edexcel International Advanced Level in Mathematics specification (issue 3)
- Pearson Edexcel IAL Decision Mathematics 1 scheme of work
Last updated 7 November 2026. Spotted a mistake? Tell us.