Overhead absorption rates and over- or under-absorption

Edexcel IAL Accounting · WAC11 The Accounting System and Costing

An overhead absorption rate (OAR) charges each department's overheads to products. Because it is set from budgets, actual overheads absorbed rarely equal actual overheads incurred (spec 1.4.10 and 1.4.11).

Practise this in the app: instant marking and a fix for every mistake. Free, no email needed to start.

Practise this lesson

Machine hour and labour hour rates

OAR = budgeted overheads / budgeted activity, set at the start of the period.

Each department has its own rate. The 2024 examiners' report noted some candidates added labour hours and machine hours together as one divisor: never do this; use the one basis that suits each department.

MachiningAssembly
Budgeted overheads£96,000£72,000
Budgeted activity12,000 machine hours18,000 labour hours
OAR£8.00 per machine hour£4.00 per labour hour

Over- and under-absorption

Overheads absorbed = OAR x actual activity. Compare with actual overheads:

Causes: actual overheads different from budget, and/or actual activity different from budget.

Machining £Assembly £
Overheads absorbed102,400 (12,800 x £8)68,800 (17,200 x £4)
Actual overheads99,50070,100
Over / (under) absorbed2,900(1,300)

Using absorption rates

OARs let a business cost a job or product as soon as it is made, without waiting for actual overhead totals at the year end; this supports pricing and quotes. Limitations: rates are based on estimates, the choice of basis is a judgement, and fixed overheads absorbed per unit change if activity changes. The June 2024 examiners' report noted that over- or under-recovery was often not attempted: practise it.

Worked example

Find the over- or under-absorption in each department.

  1. Machining: absorbed 102,400, actual 99,500: over-absorbed by 2,900.
  2. Assembly: absorbed 68,800, actual 70,100: under-absorbed by 1,300.

Answer: Machining over-absorbed £2,900 (add to profit); Assembly under-absorbed £1,300 (extra expense).

Key idea: OAR = budgeted overheads / budgeted hours. Absorbed = OAR x actual hours. Over-absorbed: add to profit; under-absorbed: extra expense.

Check yourself

  1. A department's budgeted overheads are £135,000 and budgeted machine hours are 9,000. Calculate the machine hour rate.
    Show answer

    £15.00. 135,000 / 9,000 = £15.00 per machine hour.

  2. The OAR is £6.50 per direct labour hour. Actual direct labour hours were 14,200. Calculate the overheads absorbed.
    Show answer

    £92300. 6.50 x 14,200 = 92,300.

  3. Overheads absorbed were £92,300 and actual overheads were £88,750. By how much were overheads over-absorbed?
    Show answer

    £3550. 92,300 - 88,750 = 3,550, added to profit.

  4. Budgeted overheads £60,000; budgeted labour hours 15,000. Actual hours 13,800; actual overheads £61,200. Calculate the under-absorption.
    Show answer

    £6000. OAR £4; absorbed 4 x 13,800 = 55,200; under-absorbed = 61,200 - 55,200 = 6,000.

  5. A department is highly automated, with a few staff supervising many machines. Which absorption basis is most suitable?
    • Machine hours
    • Direct labour hours
    • Machine hours plus labour hours added together
    • Number of employees
    Show answer

    Machine hours. Overheads are driven by machine time.

  6. Overheads have been under-absorbed. How is this treated at the end of the period?
    • As extra income, increasing profit
    • Added to closing inventory
    • As an additional expense, reducing profit
    • Ignored, as it is only an estimate
    Show answer

    As an additional expense, reducing profit. Products were undercharged, so the shortfall is charged against profit.

Practise with instant feedback