Standard costing: purpose and setting up a system
Edexcel IAL Accounting · WAC12 Corporate and Management Accounting
A standard cost is a predetermined cost of making one unit under expected conditions. Comparing actual costs with standards produces variances that show where performance differed from plan.
Purpose
Standard costing helps a business:
- control costs by comparing actual with standard and investigating variances
- set budgets (standard cost x planned output)
- set selling prices and quote for orders
- value inventory consistently
- motivate staff with clear targets and support management by exception
- assign responsibility: purchasing for material prices, production for usage and efficiency, personnel for wage rates.
Types of standard
- Ideal: perfect conditions, no waste or idle time. Rarely achieved, can demotivate.
- Attainable: allows for normal waste, breakdowns and rest; challenging but achievable. Usually best for motivation.
- Basic: a long-term base used to show trends; quickly becomes out of date.
Stages in setting up a system
1. Identify the products or cost units.
2. Set standard quantities: material per unit from product specifications and past usage records (allowing for normal wastage); labour hours from work study (time and motion) and past time sheets.
3. Set standard prices: material prices from supplier quotations, purchase invoices and stores record cards; wage rates from the payroll and wage agreements.
4. Set overhead absorption rates from overhead budgets and budgeted activity.
5. Record everything on a standard cost card.
6. Collect actual costs from the accounting records, calculate variances, report them and review the standards regularly.
The specification stresses collecting data from accounting records: stores record cards, invoices, payroll and time sheets.
Using a stores record card
When material is bought at different prices, the actual price is the weighted average, not the last price on the card (an examiner warning). Receipts: 2,000 m at £2.40; 3,000 m at £2.55; 1,000 m at £2.70.
Average price = total cost / total quantity = £15,150 / 6,000 = £2.5250 per metre.
Worked example
Prepare a standard cost card for one chair: 2.5 m of fabric at £4.00 per m; 1.5 hours of labour at £12.00 per hour; variable overhead £3.00 per labour hour; fixed overhead absorbed at £5.00 per labour hour.
- Materials 2.5 x 4.00 = £10.00
- Labour 1.5 x 12.00 = £18.00
- Variable overhead 1.5 x 3.00 = £4.50
- Fixed overhead 1.5 x 5.00 = £7.50
Answer: Standard cost per chair £40.00
Check yourself
- A product needs 4 kg of material at £2.50 per kg and 2 hours of labour at £11 per hour. Overheads are absorbed at £6 per labour hour. Calculate the standard cost per unit.
Show answer
£44.00. 10 + 22 + 12 = £44.00.
- A stores card shows receipts of 500 kg at £3.20, 1,500 kg at £3.40 and 1,000 kg at £3.65. Calculate the weighted average price per kg to 2 decimal places.
Show answer
£3.45. (1,600 + 5,100 + 3,650) / 3,000 = £3.45.
- The standard cost of a unit is £38.50. Budgeted production is 2,400 units. What is the budgeted production cost?
Show answer
£92400. 38.50 x 2,400 = £92,400.
- Which type of standard is usually best for motivating staff?
- Ideal standard
- Basic standard
- Attainable standard
- Historic actual cost
Show answer
Attainable standard. Attainable standards are challenging but achievable.
- Which source is most appropriate for setting standard labour times?
- Work study (time and motion) and past time sheets
- Supplier price lists
- The share register
- The statement of cash flows
Show answer
Work study (time and motion) and past time sheets. Work study measures how long tasks should take.
- Which record is a source for setting standard material prices?
- Labour time sheets
- The directors' report
- Purchase invoices and supplier quotations
- Customer invoices
Show answer
Purchase invoices and supplier quotations. Prices paid and quoted for materials come from invoices and quotations.
Sources
- Pearson Edexcel International Advanced Subsidiary/Advanced Level in Accounting specification (XAC11/YAC11), Issue 2
- Pearson Edexcel IAL Accounting WAC12 examiners' report, October 2022
- Pearson Edexcel IAL Accounting WAC12 Unit 2 mark scheme, October 2022
Last updated 8 November 2026. Spotted a mistake? Tell us.