All subjects · Accounting · WAC12 Corporate and Management Accounting
Reasons for variances, interrelationships and management by exception
Edexcel IAL Accounting · WAC12 Corporate and Management Accounting
Calculating variances is only half the job. Examiners reward explaining why they arose, how one variance can cause another, and which ones deserve management's attention.
Possible reasons
| Variance | Favourable reasons | Adverse reasons |
|---|---|---|
| Material price | Bulk discounts, cheaper supplier, lower quality material, market price fall | Supplier price rises, higher quality material, loss of discounts, rush orders, exchange rate changes |
| Material usage | Better quality material, skilled workers, new machinery, less waste | Poor quality material, inexperienced staff, machine faults, theft, poor storage |
| Labour rate | Lower-paid or less skilled staff used, less overtime | Pay rise, overtime or bonus payments, more skilled (dearer) staff |
| Labour efficiency | Skilled or motivated workers, better machines, good material | Untrained staff, poor material, machine breakdowns, idle time, low morale |
| Variable overhead | Lower power prices, efficient use of machines | Higher energy prices, more hours worked |
| Fixed overhead | Spending below budget, output above budget | Spending above budget (rent rise), output below budget |
Interrelationships
Variances are often linked, so a 'good' variance in one department may cause a 'bad' one elsewhere:
- Cheaper, poorer material: material price F, but usage A (more waste) and labour efficiency A (slower working).
- More skilled, dearer workers: labour rate A, but efficiency F and material usage F.
- Overtime to meet a rush order: labour rate A, and fixed overhead may be F (higher output absorbs more).
So do not judge a manager on one variance alone; look at the whole picture and the reasons.
Management by exception
Managers have limited time, so they investigate only significant variances: for example, those over a set percentage (say 5%) of standard cost or over a money limit. Small variances are accepted as normal.
Advantages: saves management time, focuses attention where action is needed.
Disadvantages: small adverse variances that persist may be ignored; favourable variances also deserve investigation (they may show standards are too easy, or quality has been cut).
When asked whether to take action, examiners expect points for and against, reference to management by exception, and a conclusion.
Worked example
A purchasing manager reports a material price variance of £3,000 favourable after switching suppliers. The production manager reports material usage £4,200 adverse and labour efficiency £1,800 adverse. Comment.
- The cheaper material is probably lower quality, causing more waste and slower working
- Net effect = 3,000 - 4,200 - 1,800 = (£3,000)
- The switch has cost the company overall; return to the original supplier unless quality can be improved
Answer: Overall the change is £3,000 adverse: the variances are interrelated
Check yourself
- A company buys cheaper, lower-grade material. Which pattern of variances is most likely?
- Material price adverse, material usage favourable
- Material price favourable, material usage adverse
- Labour rate adverse, labour efficiency favourable
- All variances favourable
Show answer
Material price favourable, material usage adverse. Lower price saves money per kg but more is wasted.
- Highly skilled workers on higher pay are used instead of trainees. Which pattern is most likely?
- Labour rate favourable, labour efficiency adverse
- Material price adverse
- Fixed overhead adverse
- Labour rate adverse, labour efficiency favourable
Show answer
Labour rate adverse, labour efficiency favourable. They cost more per hour but work faster and waste less.
- What is management by exception?
- Investigating every variance however small
- Investigating only variances that are significant
- Ignoring all favourable variances
- Setting standards without managers' involvement
Show answer
Investigating only variances that are significant. Attention is focused on significant deviations.
- The standard material cost is £56,000 and the material variance is £3,360 adverse. The company investigates variances above 5% of standard. What is the variance as a percentage of standard?
Show answer
6.0 %. 3,360 / 56,000 x 100 = 6.0%, so it is investigated.
- Why should a large favourable variance also be investigated?
- The standard may be too easy, or quality may have been cut
- Favourable variances are always errors
- It must be paid to the shareholders
- It increases the tax charge
Show answer
The standard may be too easy, or quality may have been cut. Favourable variances may reveal slack standards or hidden problems.
- Give two possible reasons for an adverse labour rate variance.
Show answer
A pay rise was agreed after the standard was set, and overtime was paid at a premium rate to meet extra orders; more skilled, higher-paid workers may also have been used.. Labour rate variances come from the price of labour: pay rises, overtime premiums, bonuses or using a higher grade of worker.
Sources
- Pearson Edexcel International Advanced Subsidiary/Advanced Level in Accounting specification (XAC11/YAC11), Issue 2
- Pearson Edexcel IAL Accounting WAC12 Unit 2 mark scheme, June 2022
- Pearson Edexcel IAL Accounting WAC12 examiners' report, October 2022
Last updated 8 November 2026. Spotted a mistake? Tell us.