Agile approaches build a system in short cycles, delivering working parts frequently and responding to change. You need agile's concept and features, its phases, and the activities of scrum and sprints. The June 2025 paper's 12-mark essay was on a development method: strong answers covered benefits and drawbacks and applied them to the context (spec 15.3).
Concept and features
Agile is a family of approaches that develop software in short cycles, with close and continuous involvement of the customer and the ability to change requirements as the project goes on.
- Iterative: the same cycle (plan, design, develop, test, review) is repeated many times, refining the product each time based on feedback.
- Incremental: each cycle adds a working piece of functionality, so the product grows in usable increments; the most valuable features are built first.
Other features: working software is valued over heavy documentation; small, self-organising, cross-functional teams; frequent communication (often face to face or daily); continuous testing and integration.
Agile phases
| Phase | What happens |
|---|---|
| Requirements | Gather user needs as short user stories ('As a student I want to see my timetable so that I know where to go'); put them in a prioritised product backlog |
| Plan | Choose the highest-priority stories for the next iteration; estimate effort; agree the iteration goal |
| Design | Design just enough for the chosen stories: data, interface, logic |
| Develop | Code and test the stories; integrate them with the existing product |
| Release | Deliver a working increment to users; collect feedback, which feeds the next cycle's requirements |
The phases repeat in each iteration.
Scrum and sprints
Scrum is a popular agile framework.
- Roles: the product owner represents the customer and prioritises the product backlog; the scrum master helps the team follow scrum and removes obstacles; the Developers build the product (the 2020 Scrum Guide replaced the term 'development team' with Developers in one Scrum Team).
- A sprint is a fixed-length event of one month or less (often two weeks) in which the team turns selected backlog items into a working increment; a new sprint starts as soon as one ends.
- Events: sprint planning (choose items for the sprint backlog); daily scrum or stand-up (a 15-minute event where the Developers inspect progress towards the sprint goal and adapt their plan; many teams use the older questions: what I did yesterday, what I will do today, any blockers); sprint review (demonstrate the increment to stakeholders and get feedback); sprint retrospective (the team discusses how to improve its way of working).
- The backlog is reprioritised after each sprint, so changes are welcomed rather than resisted.
Advantages and disadvantages
Advantages: copes well with changing or unclear requirements; users see working software early and often, so misunderstandings are caught early; the most valuable features are delivered first, so benefits start sooner; continuous testing improves quality; high customer satisfaction and team motivation.
Disadvantages: needs the customer's time and commitment throughout; final cost and delivery date are hard to predict at the start; scope can keep growing; less documentation can make maintenance harder; works best with small, experienced, co-located teams; can be hard to apply to fixed-price contracts or heavily regulated projects.
Agile versus waterfall: choose agile when requirements are likely to change and the client can be closely involved; choose waterfall when requirements are fixed, documentation is essential and the timetable and budget must be agreed up front.
Worked example
A start-up is building a fitness app and is unsure which features users will want. Evaluate the use of agile (brief plan of a 12-mark answer).
- For: requirements are uncertain, so iterative sprints let the team release a basic app quickly and add features based on real user feedback.
- For: incremental releases mean the start-up can earn revenue and attract investors earlier.
- Against: the founders must act as product owner and give regular time; cost and launch date of the full app are hard to fix, which may worry investors.
- Against: light documentation could hinder new developers as the company grows.
- Judgement: agile is the better choice because uncertainty about features is the biggest risk, provided the founders commit to sprint reviews and keep a prioritised backlog.
Answer: A supported conclusion weighs both sides in context
Check yourself
- What does 'incremental' mean in agile development?
- All the code is written at the end
- Each cycle adds a working piece of functionality to the product
- Requirements are fixed at the start
- Each phase is signed off before the next
Show answer
Each cycle adds a working piece of functionality to the product. The product grows in usable increments.
- What does 'iterative' mean in agile development?
- The project has one long phase
- Testing happens only once
- There is no planning
- The development cycle is repeated, refining the product each time from feedback
Show answer
The development cycle is repeated, refining the product each time from feedback. Repeated cycles.
- Who prioritises the product backlog in scrum?
- The scrum master
- The product owner
- The newest developer
- The database administrator
Show answer
The product owner. The product owner represents the customer.
- What is the purpose of the daily scrum?
- A full demonstration to the client
- A review of the whole project budget
- A short meeting where team members share progress, plans and blockers
- A meeting to write the requirements specification
Show answer
A short meeting where team members share progress, plans and blockers. Coordination and spotting obstacles.
- What happens in a sprint retrospective?
- The team reflects on how it worked and agrees improvements
- The product is demonstrated to stakeholders
- The final system is installed
- Requirements are frozen for the rest of the project
Show answer
The team reflects on how it worked and agrees improvements. Improving the process.
- Which is a disadvantage of agile development?
- Users never see working software
- Requirements cannot change
- The final cost and completion date are hard to predict at the start
- There is no testing
Show answer
The final cost and completion date are hard to predict at the start. Flexible scope makes estimates harder.
- Explain why agile is better than waterfall when a client's requirements are likely to change.
Show answer
Agile works in short iterations and reprioritises the backlog after each one, so new or changed requirements can be included in the next sprint without redoing the whole project.. Short cycles, so changes absorbed.
Sources
- Pearson Edexcel International Advanced Level in Information Technology specification (first teaching 2018), Issue 2, February 2021
- Pearson Edexcel IAL Information Technology: scheme of work for Unit 3
- Pearson Edexcel IAL Information Technology WIT13/01 examiners' report, June 2025 series
- Scrum.org: navigating Scrum events, the Sprint (quoting the Scrum Guide)
- Scrum.org: what is a Daily Scrum?
Last updated 8 November 2026. Spotted a mistake? Tell us.