The waterfall method
Edexcel IAL Information Technology · WIT13 2 hour written exam on data, enabling technologies and systems development
The waterfall method develops a system in a fixed sequence of phases, each finished and signed off before the next begins. You need its concept, features, phases and the activities in each phase (spec 15.2).
Concept and features
The waterfall method is a linear, sequential approach: like water flowing down steps, each phase flows into the next.
Features:
- requirements are fixed and fully documented at the start;
- each phase has defined deliverables (documents, designs, code) and is signed off before the next begins;
- going back to an earlier phase is difficult and costly;
- the client sees the working system only near the end;
- heavy emphasis on documentation.
Phases and activities
| Phase | Activities |
|---|---|
| Requirements / analysis | Investigate the current system (interviews, questionnaires, observation, document analysis); identify problems and user needs; feasibility study; produce a requirements specification agreed and signed by the client |
| Design | Design data structures (normalised tables, data dictionary), inputs and outputs, user interface, processes and algorithms, security, hardware and network; plan testing |
| Implementation | Write the code, build the database and interface according to the design; unit test individual modules |
| Testing / debugging | Integration and system testing against the requirements; test plans with normal, boundary and erroneous data; fix bugs; user acceptance testing by the client |
| Installation | Install hardware and software; convert and migrate data; choose a changeover method; train users; hand over user and technical documentation |
| Maintenance | Corrective, adaptive and perfective maintenance after the system is in use; review against the original requirements |
Advantages and disadvantages
Advantages: simple to understand and manage; clear milestones and deliverables make progress easy to track; thorough documentation helps maintenance and new staff; costs and timescales can be estimated early; suits projects with stable, well-understood requirements, fixed contracts, or strict regulation and safety requirements.
Disadvantages: inflexible: changes to requirements are hard and expensive after sign-off; users see the product late, so misunderstandings are found late, when they cost most to fix; testing comes late, so serious errors may be found near the deadline; long time before any working software is delivered; risky for large, complex or innovative projects.
Worked example
A government agency must build a tax calculation system to a fixed legal specification by a fixed date. Explain why waterfall might suit it.
- The requirements are set by law and unlikely to change, so fixing them at the start is realistic.
- Each phase is signed off and documented, which gives the audit trail a government body needs.
- Clear milestones help track progress against the fixed deadline and budget.
Answer: Stable requirements, documentation and control make waterfall a good fit
Check yourself
- Which phase comes immediately after design in the waterfall method?
- Requirements
- Testing
- Installation
- Implementation
Show answer
Implementation. Design, then implementation (coding).
- In which waterfall phase are interviews and questionnaires used to investigate users' needs?
- Implementation
- Requirements / analysis
- Installation
- Maintenance
Show answer
Requirements / analysis. Fact-finding happens at the start.
- Data migration, user training and choosing a changeover method happen in which phase?
- Design
- Requirements
- Testing
- Installation
Show answer
Installation. Getting the system into use.
- What is the main disadvantage of the waterfall method?
- Changing requirements after sign-off is difficult and costly
- It produces no documentation
- There are no clear milestones
- It cannot be used for databases
Show answer
Changing requirements after sign-off is difficult and costly. Inflexibility.
- Which project is most suited to the waterfall method?
- A start-up app whose features will change after user feedback
- A game whose design will evolve each month
- A system with clear, stable requirements and strict regulatory documentation
- A website whose client cannot describe what they want
Show answer
A system with clear, stable requirements and strict regulatory documentation. Stable requirements suit waterfall.
- What is user acceptance testing?
- The client tests the system to confirm it meets their requirements before accepting it
- Developers test a single function
- The system is tested only with erroneous data
- Testing the network cables
Show answer
The client tests the system to confirm it meets their requirements before accepting it. Final sign-off by the client.
- Explain why errors found late in a waterfall project are expensive to fix.
Show answer
Because each phase builds on the previous one, an error in the requirements or design means the later design, code and tests must all be redone, which costs time and money near the deadline.. Phases build on each other, so rework, so cost.
Sources
- Pearson Edexcel International Advanced Level in Information Technology specification (first teaching 2018), Issue 2, February 2021
- Pearson Edexcel IAL Information Technology: scheme of work for Unit 3
- Pearson Edexcel IAL Information Technology WIT13/01 sample assessment mark scheme
Last updated 8 November 2026. Spotted a mistake? Tell us.