Discharge by frustration and the 1943 Act

Edexcel IAL Law · YLA1/02 (Paper 2, 2.1.4)

A contract is frustrated when, after it is made, an event outside the parties' control makes performance impossible, illegal or radically different. Both parties are released for the future.

Practise this in the app: instant marking and a fix for every mistake. Free, no email needed to start.

Practise this lesson

When frustration applies

When it does not apply

Law Reform (Frustrated Contracts) Act 1943

Worked example

Problem: A band books a hall for a concert and pays a deposit of 10000 dollars. Before the date, the hall burns down without fault. The hall owner spent 2500 dollars preparing for the event. What happens to the deposit?

  1. Issue: is the contract frustrated?
  2. Rule: destruction of the subject matter frustrates a contract (Taylor v Caldwell).
  3. Apply: under s1(2) the deposit is recoverable, but the court may allow the owner to keep up to 2500 for expenses.
  4. Conclusion: the band likely recovers 7500 to 10000 dollars, at the court's discretion.

Answer: Frustrated; deposit recoverable, less up to 2500 for expenses.

Key idea: Frustration: a later event, not the parties' fault, makes performance impossible, illegal or radically different (Taylor v Caldwell, Krell v Henry). Not frustration: mere expense (Davis Contractors), self-induced events, foreseeable risks. The 1943 Act s1(2) returns money paid, less just expenses.

Check yourself

  1. Krell v Henry is authority that a contract can be frustrated when
    • the subject matter is destroyed by fire
    • performance becomes more expensive
    • one party changes its mind
    • an outside event destroys its whole commercial purpose
    Show answer

    an outside event destroys its whole commercial purpose. Loss of the entire commercial purpose.

  2. Why is Herne Bay Steam Boat v Hutton contrasted with Krell v Henry?
    • The boat sank, so there was frustration
    • The whole purpose was not lost, so there was no frustration
    • The hirer was at fault
    • The contract was illegal
    Show answer

    The whole purpose was not lost, so there was no frustration. Frustration requires loss of the whole commercial purpose.

  3. A builder's costs rise sharply because of a shortage of workers. Applying Davis Contractors v Fareham, the contract is
    • frustrated automatically
    • void for mistake
    • frustrated if the builder is losing money
    • not frustrated, because it is only more expensive to perform
    Show answer

    not frustrated, because it is only more expensive to perform. Hardship or expense is not frustration.

  4. Maritime National Fish v Ocean Trawlers shows there is no frustration where
    • the party relying on it caused the problem by its own choice
    • the subject matter is destroyed
    • performance becomes illegal
    • a performer falls ill
    Show answer

    the party relying on it caused the problem by its own choice. Self-induced frustration does not count.

  5. A buyer paid a 10000 dollar deposit before a contract was frustrated. The court allows the seller to keep 2500 for expenses under s1(2) of the 1943 Act. How much does the buyer recover?
    Show answer

    7500 dollars. 10000 - 2500 = 7500.

  6. Define frustration of contract.
    Show answer

    An event after the contract is made, which is not the fault of either party, makes performance impossible, illegal or radically different, so the contract ends.. Three ingredients: later event, no fault, impossibility or radical change.