Planning tools: precedence tables, Gantt charts and critical path analysis
Edexcel IAL Information Technology · WIT13 2 hour written exam on data, enabling technologies and systems development
Project managers use precedence tables, network (node) diagrams, critical path analysis and Gantt charts to plan and track IT projects. You must be able to interpret and produce them. In June 2025, candidates lost marks on a Gantt chart and critical path question by missing dependencies and early start dates and by drawing imprecise arrows (spec 15.1.5 and 15.1.6).
Requirements and precedence tables
Planning starts from the requirements: what the project must deliver, broken down into tasks (activities), each with a duration and the resources needed.
A precedence table lists every task, its duration and its immediate predecessors (the tasks that must finish before it can start: a finish-to-start dependency).
| Task | Description | Duration (days) | Depends on |
|---|---|---|---|
| A | Requirements | 3 | none |
| B | Design | 4 | A |
| C | Build database | 5 | B |
| D | Build interface | 3 | B |
| E | Testing | 2 | C, D |
| F | Train staff | 2 | B |
| G | Install | 1 | E, F |
Nodes and critical path analysis (CPA)
In an activity-on-node diagram each task is a box (node) and arrows show dependencies. Each node can show the task, duration, earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF).
- Forward pass: ES of a task = the largest EF of its predecessors; EF = ES + duration.
- Backward pass: LF of a task = the smallest LS of its successors (the last task's LF = project duration); LS = LF - duration.
- Float (slack) = LS - ES: how long a task can be delayed without delaying the project.
- The critical path is the chain of tasks with zero float; its total duration is the minimum project duration. Any delay to a critical task delays the whole project.
Some Pearson questions use an activity-on-arc network instead (the June 2024 paper asked candidates to complete one): each activity is an arrow labelled with its letter and duration, and the circles (nodes) are events showing the earliest and latest event times. The forward and backward passes work the same way.
PERT is a related technique used when task durations are uncertain (it uses optimistic, likely and pessimistic estimates).
| Task | ES | EF | LS | LF | Float |
|---|---|---|---|---|---|
| A | 0 | 3 | 0 | 3 | 0 |
| B | 3 | 7 | 3 | 7 | 0 |
| C | 7 | 12 | 7 | 12 | 0 |
| D | 7 | 10 | 9 | 12 | 2 |
| E | 12 | 14 | 12 | 14 | 0 |
| F | 7 | 9 | 12 | 14 | 5 |
| G | 14 | 15 | 14 | 15 | 0 |
Critical path A > B > C > E > G, duration 15 days
Gantt charts
A Gantt chart is a bar chart against a time scale: one row per task, a bar from its start to its finish. It shows at a glance what should be happening when, overlaps, milestones (diamonds) and progress (bars shaded as tasks complete). Dependencies can be shown with arrows from the end of one bar to the start of the next.
Drawing one in the exam: list tasks in order; draw each bar starting at its earliest start after all its predecessors finish; make lengths match durations exactly; add precise dependency arrows; mark the critical path if asked; label the time axis.
Strengths: easy to read and communicate; good for tracking progress and resources. Weaknesses: dependencies and float are less clear than on a network diagram; becomes cluttered for large projects; must be updated as things change.
Interpreting the tools
- 'Task D is delayed by 1 day: does the project finish later?' Compare the delay with its float: D has float 2, so a 1-day delay is absorbed.
- 'Which tasks can run at the same time?' Those whose time bars overlap with no dependency between them (C, D and F after B).
- 'What happens if a critical task overruns?' The project end date moves by the same amount, unless resources are added (crashing) or other tasks are overlapped.
- Resource conflicts: if C and D need the same developer, they cannot both run in parallel; the schedule must change.
Worked example
For the precedence table: P (2, none), Q (5, after P), R (3, after P), S (4, after R), T (2, after Q and S). Find the critical path, duration and the float of Q.
- Forward pass: P 0 to 2; Q 2 to 7; R 2 to 5; S 5 to 9; T starts at max(7, 9) = 9, finishes 11
- Project duration = 11 days
- Backward pass: T LS 9; Q LF 9, LS 4; S LF 9, LS 5; R LS 2; P LS 0
- Float of Q = LS - ES = 4 - 2 = 2
- Critical path: P > R > S > T
Answer: Critical path P > R > S > T, 11 days; Q has 2 days of float
Check yourself
- Using the precedence table in this lesson (tasks A to G), what is the minimum project duration in days?
Show answer
15 days. The critical path A > B > C > E > G totals 15 days.
- In the lesson's project, what is the earliest start of task E (Testing), in days from the start?
Show answer
12. E needs C (finishes 12) and D (finishes 10); ES = max = 12.
- In the lesson's project, how many days of float does task F (Train staff) have?
Show answer
5. F: ES 7, LS 12; float = 5.
- In the lesson's project, how many days of float does task D (Build interface) have?
Show answer
2. D: ES 7, LS 9; float = 2.
- In the lesson's project, task C is delayed by 2 days. What is the new project duration?
Show answer
17 days. C is critical, so the whole project is delayed by 2 days.
- Tasks: J (4, none), K (6, after J), L (3, after J), M (2, after K and L). What is the minimum project duration?
Show answer
12 days. J 0 to 4, K 4 to 10, L 4 to 7, M starts at 10 and ends at 12.
- What is true of every task on the critical path?
- It is the shortest task
- It can be delayed without effect
- It has zero float, so any delay to it delays the whole project
- It has no predecessors
Show answer
It has zero float, so any delay to it delays the whole project. Critical tasks have no slack.
- Which is a weakness of a Gantt chart compared with a network (node) diagram?
- It cannot show task durations
- It cannot show a timeline
- It cannot show progress
- Dependencies between tasks and float are harder to see
Show answer
Dependencies between tasks and float are harder to see. Network diagrams show dependencies explicitly.
Sources
- Pearson Edexcel International Advanced Level in Information Technology specification (first teaching 2018), Issue 2, February 2021
- Pearson Edexcel IAL Information Technology: scheme of work for Unit 3
- Pearson Edexcel IAL Information Technology WIT13/01 examiners' report, June 2025 series
- Pearson Edexcel IAL Information Technology WIT13/01 sample assessment mark scheme
- Pearson Edexcel IAL Information Technology WIT13/01 question paper, June 2024 series
Last updated 8 November 2026. Spotted a mistake? Tell us.