All subjects · Information Technology · WIT13 2 hour written exam on data, enabling technologies and systems development

Planning tools: precedence tables, Gantt charts and critical path analysis

Edexcel IAL Information Technology · WIT13 2 hour written exam on data, enabling technologies and systems development

Project managers use precedence tables, network (node) diagrams, critical path analysis and Gantt charts to plan and track IT projects. You must be able to interpret and produce them. In June 2025, candidates lost marks on a Gantt chart and critical path question by missing dependencies and early start dates and by drawing imprecise arrows (spec 15.1.5 and 15.1.6).

Practise this in the app: instant marking and a fix for every mistake. Free, no email needed to start.

Practise this lesson

Requirements and precedence tables

Planning starts from the requirements: what the project must deliver, broken down into tasks (activities), each with a duration and the resources needed.

A precedence table lists every task, its duration and its immediate predecessors (the tasks that must finish before it can start: a finish-to-start dependency).

TaskDescriptionDuration (days)Depends on
ARequirements3none
BDesign4A
CBuild database5B
DBuild interface3B
ETesting2C, D
FTrain staff2B
GInstall1E, F

Nodes and critical path analysis (CPA)

In an activity-on-node diagram each task is a box (node) and arrows show dependencies. Each node can show the task, duration, earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF).

Some Pearson questions use an activity-on-arc network instead (the June 2024 paper asked candidates to complete one): each activity is an arrow labelled with its letter and duration, and the circles (nodes) are events showing the earliest and latest event times. The forward and backward passes work the same way.

PERT is a related technique used when task durations are uncertain (it uses optimistic, likely and pessimistic estimates).

TaskESEFLSLFFloat
A03030
B37370
C7127120
D7109122
E121412140
F7912145
G141514150

Critical path A > B > C > E > G, duration 15 days

Gantt charts

A Gantt chart is a bar chart against a time scale: one row per task, a bar from its start to its finish. It shows at a glance what should be happening when, overlaps, milestones (diamonds) and progress (bars shaded as tasks complete). Dependencies can be shown with arrows from the end of one bar to the start of the next.

Drawing one in the exam: list tasks in order; draw each bar starting at its earliest start after all its predecessors finish; make lengths match durations exactly; add precise dependency arrows; mark the critical path if asked; label the time axis.

Strengths: easy to read and communicate; good for tracking progress and resources. Weaknesses: dependencies and float are less clear than on a network diagram; becomes cluttered for large projects; must be updated as things change.

Interpreting the tools

Worked example

For the precedence table: P (2, none), Q (5, after P), R (3, after P), S (4, after R), T (2, after Q and S). Find the critical path, duration and the float of Q.

  1. Forward pass: P 0 to 2; Q 2 to 7; R 2 to 5; S 5 to 9; T starts at max(7, 9) = 9, finishes 11
  2. Project duration = 11 days
  3. Backward pass: T LS 9; Q LF 9, LS 4; S LF 9, LS 5; R LS 2; P LS 0
  4. Float of Q = LS - ES = 4 - 2 = 2
  5. Critical path: P > R > S > T

Answer: Critical path P > R > S > T, 11 days; Q has 2 days of float

Key idea: Precedence table: tasks, durations, predecessors. Forward pass gives earliest times (take the largest), backward pass latest times (take the smallest). Float = LS - ES. Zero-float tasks form the critical path, which fixes the minimum duration. Gantt charts show tasks as bars on a timeline.

Check yourself

  1. Using the precedence table in this lesson (tasks A to G), what is the minimum project duration in days?
    Show answer

    15 days. The critical path A > B > C > E > G totals 15 days.

  2. In the lesson's project, what is the earliest start of task E (Testing), in days from the start?
    Show answer

    12. E needs C (finishes 12) and D (finishes 10); ES = max = 12.

  3. In the lesson's project, how many days of float does task F (Train staff) have?
    Show answer

    5. F: ES 7, LS 12; float = 5.

  4. In the lesson's project, how many days of float does task D (Build interface) have?
    Show answer

    2. D: ES 7, LS 9; float = 2.

  5. In the lesson's project, task C is delayed by 2 days. What is the new project duration?
    Show answer

    17 days. C is critical, so the whole project is delayed by 2 days.

  6. Tasks: J (4, none), K (6, after J), L (3, after J), M (2, after K and L). What is the minimum project duration?
    Show answer

    12 days. J 0 to 4, K 4 to 10, L 4 to 7, M starts at 10 and ends at 12.

  7. What is true of every task on the critical path?
    • It is the shortest task
    • It can be delayed without effect
    • It has zero float, so any delay to it delays the whole project
    • It has no predecessors
    Show answer

    It has zero float, so any delay to it delays the whole project. Critical tasks have no slack.

  8. Which is a weakness of a Gantt chart compared with a network (node) diagram?
    • It cannot show task durations
    • It cannot show a timeline
    • It cannot show progress
    • Dependencies between tasks and float are harder to see
    Show answer

    Dependencies between tasks and float are harder to see. Network diagrams show dependencies explicitly.

Practise with instant feedback

Sources

Last updated 8 November 2026. Spotted a mistake? Tell us.